2027 Method
Changes 0
M

ViewSchedule.CreateMaterialTakeoff

Description:
Creates a material takeoff.
Remarks:
A material takeoff is a schedule that displays information about the materials that make up elements in the model. Unlike regular schedules where each row (before grouping) represents a single element, each row in a material takeoff represents a single <element, material> pair.
public static ViewSchedule CreateMaterialTakeoff(
	Document document,
	ElementId categoryId
)
  • document
    The document to which the new schedule will be added.
  • categoryId
    The ID of the category whose elements will be included in the schedule, or InvalidElementId for a multi-category schedule.
Return Value ViewSchedule The newly created schedule.
  • document is not a project document. -or- categoryId is not a valid category for a material takeoff.
  • A non-optional argument was null
  • The document is in failure mode: an operation has failed, and Revit requires the user to either cancel the operation or fix the problem (usually by deleting certain elements). -or- The document is being loaded, or is in the midst of another sensitive process.
  • The document has no open transaction.